How long would it take to build 30 miles of Roman road?

score:19

Accepted answer

Tough to narrow this down, but at least a couple sources make what may be a useful comparison to more recent construction of Scottish military roads in the 1700s.

from The Secret History of the Roman Roads of Britain: And their Impact on Military History, By M.C. Bishop

Direct comparison is obviously difficult, not least because there would inevitably be special circumstances surrounding the construction of roads in highland terrain, but it can at least provide some hints at what would have been possible in the Roman period. The expected rate of construction was 1 1/2 yards (1.35m) per man per day (at 16ft - 4.8m- most roads were just over 5 yards wide), and in at least one case 2 yards per man per day was achieved.

A second source , The Planning of Roman Roads and Walls in Northern Britain By John Poulter, references the same Scottish constructions as a proxy, and gives some numbers on the crew sizes:

enter image description here

So the bottom line figures out to 1 1/2 yards (1.35m) to 2 yds per man per day, assuming a typical 16ft wide Roman style road.

Note the last figure speaks of building a road 28 miles long in a single work season, which the book mentions was April to October. Reasonably close to your requested 30 mile road.

Upvote:6

I don't know if this helps: but the Via Appia between Rome and Capua was built in 4 years (312 - 308 BC) The distance is disputed but was more than 100 miles. See EngineeringRome.org